Start with your operation, not the building, then verify three things separately for each site: that the power you need can be delivered, that the trucks you run can move through the site, and that the workforce you need can be recruited and kept. A building that clears one of the three can still fail on another, so compare every alternative on the same basis, in that order.
Most searches do the opposite. They shortlist buildings on rent, size and clear height, then confirm power, access and labor on the one site that survives. By then the commitment is close and the options are narrow.
Three questions, three different kinds of proof
For each variable, “available” is a starting point, not due diligence.
Power: a listing says the building “has power.” What you need to know is whether this site can deliver the capacity your operation needs, on your schedule. The utility and a qualified electrical engineer can verify it.
Truck access: a listing says the building has docks and is near the highway. What you need to know is whether your trucks, trailers and shift-change traffic can move through this specific site. Verify it with a site walk with your operations team and a transportation review.
Labor: a market report says the market has a large industrial workforce. What you need to know is whether this site can recruit and retain your workforce, at your wage, on your shifts. Local employers, workforce agencies and a labor analytics provider can verify it.
We cover power and labor in depth in The Power Readiness Framework and The Labor Readiness Framework.
Step 1: Define the operation, not the building
Before touring anything, write down what the operation needs in business terms: the electrical load now and in five to ten years, headcount and shift structure, the wage band the business case supports, and the truck and trailer volume at peak. Your operations leader usually knows most of this. Every later step is tested against it.
Step 2: Power. Available is not deliverable
A building that “has power” may not have the capacity your operation needs, and a market with strong overall capacity may still have a constrained connection at one site. Verify existing service, utility capacity and upgrade scope, cost, responsibility and timeline before you commit. The utility and a qualified engineer answer these, not the landlord or an advisor.
Step 3: Truck access. Look at how the site works, not just where it sits
Truck access is more than a highway exit nearby. For each site, walk it with your operations team and test these against your own volumes:
Truck court depth, dock positions, and trailer storage relative to your peak.
Entry and exit paths, turning radii, and how trucks queue.
Whether employee traffic and truck traffic are separated at shift change.
How the site connects to the highways, rail, port or intermodal facilities your freight actually uses.
A site can look close on a map and still fail on the yard, which is why this belongs in the real estate process from the start.
Step 4: Labor. Available is not accessible
A large regional workforce does not mean this site can staff your shifts. The labor shed, the area workers will actually commute from, belongs to the address, not the market. In a market where most qualified workers are already employed, you will likely be recruiting against incumbents instead of hiring from slack, which changes both cost and ramp time. Verify applicant flow, turnover, and the drive-time labor shed for each site.
Step 5: Compare every alternative on the same basis
Treat power, truck access and labor as comparison variables from the beginning of the search, applied to every site, not just the finalist. Then reflect the risk in the negotiation through term length, expansion rights, and responsibility for upgrades.
Where an advisor fits
Our role is to make sure these questions are asked early, in the right order, by the right parties, and to turn the answers into a real estate decision and a negotiation. We do not verify electrical capacity or produce the labor analysis ourselves. We make sure someone qualified does, before you sign.
Start your site selection
If a site search, relocation or lease renewal is on your horizon, start with the Site Selection Brief. It brings power, truck access and labor into the process from the first conversation. For timing, see When Should You Start Your Industrial Lease Renewal?
This article is general information, not legal, engineering or financial advice. Capacity, wage and cost figures for any site should be confirmed with the utility, a qualified engineer and local employers.
Frequently asked questions
How do I choose a warehouse location that has enough power, truck access and available labor?
Start with what your operation needs, then verify power deliverability, truck access and labor accessibility separately for every site, and compare all alternatives on the same basis. Do not confirm these only for the one site that survives every other filter.
When should I evaluate power, truck access and labor in a site search?
At the start, alongside rent and building specifications, and applied to every alternative. Confirming them last is how problems get discovered after the commitment.
If a listing says the building has power, is that enough?
No. That is a starting point, not verification. Existing service, actual capacity, and deliverability to that specific site each need to be confirmed with the utility and a qualified engineer.
What should I check for truck access beyond highway proximity?
Check truck court depth, dock positions and trailer storage against your peak volume, how trucks enter, exit and queue, and whether employee and truck traffic are separated at shift change.
What is the difference between labor available in a market and labor accessible to a site?
Regional workforce totals are drawn across a whole metro. Your building recruits from a drive-time radius around one address, and only from workers not already committed to another employer.
Can a real estate advisor confirm electrical capacity or workforce availability?
No. An advisor identifies requirements, sequences the due diligence, compares sites, and builds the negotiation around the answers. Capacity is confirmed by the utility and an engineer, and workforce data by employers, workforce agencies and analytics providers.